Replacement of a 16-bay top antenna system produced by RFS, with HCA 550 feeders in Wrocław – Ślęża, 136 m.
What usually goes along with DVB-t installation is the disassembly of an existing analogue antenna system. In 2011 we started to perform “turn – key” installations and the scope for this one included:
Ślęża and Święty Krzyż installations in 2011 belong to the most complicated projects of the kind in Poland. Due to their location, structure and on – site climate, work conditions were hard during most of our proceedings. For the needs of this contract we designed and manufactured a derrick mounted on the tower / mast top.
Replacement of a 16-bay RFS antenna system with total height of 19,5 meters and weight of 6,7 tons in Kielce – Święty Krzyż. Erection of two main feeders HCA 618. All works were done for Alcatel Lucent. The scope of the contract included:
Ślęża and Święty Krzyż installations in 2011 belong to the most complicated projects of the kind in Poland. Due to their location, structure and on – site climate, work conditions were hard during most of our proceedings. For the needs of this contract we designed and manufactured a derrick mounted on the tower / mast top.